The Federal Government has approved the commencement of procurement for the proposed East and West Super Grids, targeting an increase in electricity transmission capacity from about 5,000 megawatts to 19,000MW within two years.
Minister of Power Joseph Tegbe announced the approval on Wednesday while briefing State House correspondents after the Federal Executive Council meeting chaired by President Bola Tinubu at the Presidential Villa, Abuja. Tegbe said the projects would strengthen the national electricity network, improve resilience and enable more power to reach consumers across the country.
“The East and West Super Grids are not projects for one part of the country,” he said. “They cut across the north and south of Nigeria, strengthening the backbone that must carry power from where it is generated to where it is needed.” According to the minister, Nigeria has more than 13,000MW of available generation capacity, but the transmission network can reliably carry only about 5,000MW.
He said the proposed grids would address that imbalance, reduce instability and improve electricity supply to homes, businesses and industries. “The target is simple,” Tegbe said. “We want a grid that can evacuate the power we already have, not one that leaves generation stranded while consumers remain in darkness.”
He explained that the transmission corridors would strengthen connections from Sokoto through Abuja and other locations into parts of southern Nigeria. Beyond the super grids, the council approved three immediate interventions serving Abuja and the Lagos axis.
The first involves a 33kV double-circuit underground and overhead line connected to the Katampe Transmission Substation, a major electricity hub serving the North-Central region. The second covers the design, manufacture and supply of three 300MVA, 330/132/33kV transformers for the Ikeja West Transmission Substation, a critical supply point for Lagos.
The third project will reconstruct and upgrade the 35.6-kilometre Itumola–Mapasin–Shagamu 132kV single-circuit transmission line into a double-circuit line to meet growing demand along the Lagos–Shagamu corridor. “These are not glamorous projects, but they are the projects that determine whether power actually gets to the consumer,” Tegbe said. The minister explained that the high-capacity transformers would be manufactured abroad because Nigeria does not yet have the capacity to produce equipment of that specification.
“Some companies have started assembling transformers locally, but these large units require specialised manufacturing,” he said. “They can take between three and six months to produce, and global demand is rising because of artificial intelligence and data centres.” Tegbe also disclosed that the ministry had begun a nationwide technical audit to identify ageing and weak electricity assets requiring replacement or rehabilitation.
He said the exercise, which had been running for four weeks, divided the country into three major energy zones: Lagos and its industrial corridor, Abuja–Kaduna–Kano, and Enugu–Onitsha–Benin. “We will no longer spend money on the wrong projects,” he said. “The audit will show us exactly where the system is failing and where investment will deliver measurable impact.”